Määräaika päättynyt EU-hankinta SähköTarvikkeet

High Voltage Main Transformers

Helen Oy · alue ei tiedossa

Perustiedot

Osallistumishakemusten määräaika
ti 6.2.2024 klo 12.00 (päättynyt)
Kysymysten määräaika
ma 29.1.2024 klo 12.00 (päättynyt)
Hankkija
Helen Oy, Y-tunnus 2630573-4
Toteutuspaikka
alue ei tiedossa
Hankintalaji
Tarvikkeet ja laitteet (tavarahankinta)
Menettely
Neuvottelumenettely, EU-hankinta
Ilmoituksen tyyppi
Hankintailmoitus – Erityisalat
Arvioitu kokonaisarvo
Ei ilmoitettu
Erät
4 erää
Pääasiallinen CPV
31170000 Muuntajat
Sopimuskausi
3.6.2024–31.10.2026
Julkaistu
23.1.2024

Erät ammattialoittain

  • Sähkö: Kaikki erät

Ammattiala on Urakkahaun luokittelu. Työn sisältö ratkeaa tarjouspyyntöasiakirjoista.

Ilmoituksen teksti

Alkuperäinen teksti Hilmasta, muuttamattomana
Helen Ltd ("The Client" or "The Contracting unit") aims to be carbon neutral energy company by 2030. In order to achieve its carbon neutrality targets, Helen is currently seeking to increase non-combustion-based energy solutions for its energy production. In this procurement The Contracting unit is seeking 1-3 suppliers for high voltage main transformers, preliminary to two different production locations in Helsinki area, Finland, as described in this EU Procurement Notification and its Annexes. The main driver for electrode boiler investments is to increase the capacity of non-fossil-based district heat production. The Contracting unit will make a separate project execution decision for .for Hanasaari and Patola projects. Hanasaari project consist two main transformers (A1, and A2) which shall have identical technical characteristics. Patola project consist one (1) main transformer that have its own technical characteristics. The procurement consists of 3 parts, which may be quoted as follows: ALTERNATIVE A (parts quoted separately): A1. HaCa1 Hanasaari production site, 1 X ~110 MVA main transformer A2. HaCa2 Hanasaari production site, 1 X ~110 MVA main transformer A3. Patola production site, 1 X ~140 MVA main transformer ALTERNATIVE B (combination of parts mentioned in the alternative A): Alternative B allows Candidate to take synergy advantages into consideration and give more competitive pricing for bigger entity (2-3 transformer). The Candidate may send the application to tender for part A1, A2 and/or part A3. The Candidate may send the application for Alternative B but must then apply and tender for same parts separately (Alternative A) as well. The Supplier or Suppliers will be chosen based on the final evaluation. The economically most advantageous quotation or combination of the quotations will be chosen. Preliminary grounds for decision are described in the preliminary project description.

Erien kuvaukset

Erä 1: A1. HaCa1 Hanasaari production site, 1 X ~110 MVA main transformer
Helen Ltd is planning to increase its carbon neutral DH production in Hanasaari production site with total capacity of ~200MW. Part A1 includes 50% of the total transformer capacity for Hanasaari project. The main transformers will be installed to a new building in Hanasaari production site. The delivery includes main transformers designed, manufactured, delivered, installed, and commissioned to Hanasaari, Helsinki. The commissioning of the main transformers will take place after necessary electricity and automation installations are ready, according to the present schedule in 1-6/2026. The electric boiler units are planned to be in commercial operation by 6-9/2026. The schedule is preliminary and subject to change.
Erä 2: A3. Patola production site, 1 X ~140 MVA main transformer
Helen Ltd is planning to increase its carbon neutral DH production in Patola production site with total capacity of approximately 120MW. Part A3 includes 100% of the total transformer capacity for Patola project. The main transformers will be installed to a new building in Patola production site. The delivery includes main transformers designed, manufactured, delivered, installed, and commissioned to Patola, Helsinki. The commissioning of the main transformers will take place after necessary electricity and automation installations are ready, according to the present schedule in 1-6/2026. The electric boiler units are planned to be in commercial operation by 6-9/2026. The schedule is preliminary and subject to change.
Erä 3: B. Combination of lots A1-A3
Lot B Combination of parts mentioned in the alternative A allows Candidate to take synergy advantages into consideration and give more competitive pricing for bigger entity (2-3 transformer). The Candidate may send the application for lot B1 but must then apply for lot A1 and/or A2 and/or A3 as well.
Erä 4: A2. HaCa2 Hanasaari production site, 1 X ~110 MVA main transformer
Helen Ltd is planning to increase its carbon neutral DH production in Hanasaari production site with total capacity of ~200MW. Part A1 includes 50% of the total transformer capacity for Hanasaari project. The main transformers will be installed to a new building in Hanasaari production site. The delivery includes main transformers designed, manufactured, delivered, installed, and commissioned to Hanasaari, Helsinki. The commissioning of the main transformers will take place after necessary electricity and automation installations are ready, according to the present schedule in 1-6/2026. The electric boiler units are planned to be in commercial operation by 6-9/2026. The schedule is preliminary and subject to change.

Erät

Erä Nimi Ammattiala Arvioitu arvo CPV
1 A1. HaCa1 Hanasaari production site, 1 X ~110 MVA main transformer Sähkö – 31170000
2 A3. Patola production site, 1 X ~140 MVA main transformer Sähkö – 31170000
3 B. Combination of lots A1-A3 Sähkö – 31170000
4 A2. HaCa2 Hanasaari production site, 1 X ~110 MVA main transformer Sähkö – 31170000

Hankinnan vaiheet

  1. Hankintailmoitustämä ilmoitus

    Osallistumishakemuksia pyydettiin, määräaika 6.2.2024 klo 12.00.

  2. TulevaJälki-ilmoitus

    Ei vielä julkaistu.

Hankkijan aiemmat sähköalan tarvikehankinnat

Helen Oy: kaikki hankinnat
Julkaistu Hankinta Voittaja Sopimusarvo Tarjouksia
ratkaistu 28.11.2025 JÄLKI-ILMOITUS Helen Oy - Salmisaaren sähkönjakelun muutokset - 10 kV kojeistot ja jakelumuuntajat ABB Oy 676 056 € ei ilmoitettu
ratkaistu 28.10.2025 JÄLKI-ILMOITUS Helen Oy:n Patolan sähkökattila- ja ilmavesilämpöpumppulaitos - Säätöventtiilit Valmet Flow Control Oy 499 100 € ei ilmoitettu
ratkaistu 3.7.2025 Hanasaari (HaC) Sähkökattilalaitos, Automaatiojärjestelmä sis. suunnittelun Valmet Automation Oy 369 000 € ei ilmoitettu
ratkaistu 3.6.2025 Medium Voltage Switchgear and Busbar B. Combination of lots A1 and A2 Siemens Osakeyhtiö ei ilmoitettu 2
ratkaistu 27.12.2024 Ennakkoilmoitus suorahankinnasta / Hanasaaren ja Salmisaaren muuntajien aktiiviosien uusinta ja tehonnosto Aiottu toimittaja: Hitachi Energy Finland Oy ei ilmoitettu ei ilmoitettu

”Ei ilmoitettu” tarkoittaa, ettei ilmoituksessa ole tätä tietoa erälle tai sopimukselle; hankinnan kokonaisarvo voi silti näkyä ilmoituksen sivulla. Puitesopimuksissa arvo on enimmäisarvo.

Lähde: Hilma (hankintailmoitukset.fi)

Ilmoitus 2024-004532

Ilmoita virheestä tai pyydä poistoa